Parallel vs. sequential RFI workflow

SubmittalLink has two RFI workflows. Parallel sends the RFI to all assignees at once. Sequential routes it through ordered review steps. The project owner chooses the workflow for the whole project.

Parallel (default) Sequential
Who answers All assignees at the same time Reviewers step by step, in order
Initial ball in court All assignees Everyone on Step 1
When a response is submitted Other assignees stay ball in court The step completes and moves to the next step
Best for Most RFIs: quick questions to the architect or engineer Formal chains, like engineer → architect → owner

Parallel is the default and the most common choice.

  • Every assignee is ball in court as soon as the RFI is created, and they can all respond at the same time.
  • A response doesn’t remove the other assignees from ball in court.
  • A ball-in-court assignee can turn on Change Ball in Court to RFI Manager when responding. This hands the RFI back to the RFI manager.
  • The RFI manager can turn on Change Ball in Court to Assignees to send it back to all assignees.
  • Review steps run in order. Everyone on the current step is ball in court.
  • After all steps are complete, ball in court moves to the RFI manager.

This project setting controls when a sequential step is complete:

  • Off (default): one response from anyone on the current step completes it. Ball in court moves to the next step.
  • On: every reviewer on the current step must respond before it moves on.

RFI Sequential Requires All affects only Sequential RFIs. It has no effect on Parallel RFIs or on submittals.

  1. Go to Left menu → Settings.
  2. On the project row, open the pencil menu and click Update Project.
  3. Set RFI Workflow Type to Parallel or Sequential.
  4. (Sequential only) Turn RFI Sequential Requires All on or off.
  5. Click Update.

Use Parallel unless your RFIs must pass through reviewers in a fixed order. Parallel is the default and gets answers fastest.

Do all assignees have to respond on a parallel RFI?

Section titled “Do all assignees have to respond on a parallel RFI?”

No. Assignees respond as needed. When the question is answered, an assignee can hand ball in court to the RFI manager with Change Ball in Court to RFI Manager.

Does RFI Sequential Requires All affect submittals?

Section titled “Does RFI Sequential Requires All affect submittals?”

No. It only affects Sequential RFIs. On submittals, one response always completes a review step.

Can project managers change the RFI workflow?

Section titled “Can project managers change the RFI workflow?”

No. Only the project owner can change project settings.