Material release tracking

Material release tracking records when approved materials are released for order or fabrication, and estimates when they’ll arrive on site. Use it to spot long-lead items before they delay the job.

The project owner goes to Settings → project row → pencil menu → Update Project and turns on Track Material Release.

Where Fields
Submittal create and update form Released On · Estimate Lead Time (in weeks)
Submittal view Released On · Estimated Delivery Date
Submittals list (Columns) Released On · Est. Delivery

You enter a lead time in weeks and SubmittalLink shows the estimated delivery date.

  1. Go to Left menu → Submittals.
  2. Click Columns and add Released On and Est. Delivery.
  3. Sort or export the list to review upcoming deliveries.

How is the estimated delivery date calculated?

Section titled “How is the estimated delivery date calculated?”

On submittals, it’s the Released On date plus the Estimate Lead Time in weeks.

Why don’t I see Released On on my submittals?

Section titled “Why don’t I see Released On on my submittals?”

Track Material Release is off for the project. Only the project owner can turn it on.