Submittals in SubmittalLink

A submittal is a package of product data, shop drawings, samples, or other information that a contractor sends to the design team for review and approval before buying or installing materials. SubmittalLink tracks every submittal in a project’s submittal log. It routes each one through review steps and always shows who’s responsible for the next action.

New to submittals? Read What is a construction submittal? and The construction submittal process.

  1. An owner or project manager creates a submittal with attachments, a spec section, a due date, and one or more review steps.
  2. Reviewers on the first step get an email. The submittal is now in their court.
  3. When a reviewer responds (Approved, Approved as Noted, Revise and Resubmit, and so on), the submittal moves to the next step. See Review workflow and ball in court.
  4. After the last step, ball in court returns to the submittal manager, who closes the submittal or creates a revision.

Go to Left menu → Submittals. The list is your submittal log.

  • Quick filters: In My Court, Open, Late
  • Search across all fields and Clear All Filters
  • Columns: choose which columns to show. With material release tracking on, you can add Released On and Est. Delivery.
  • Export PDF: download the submittal log as a PDF. Available to everyone.
Action Who
View / Respond Everyone (Respond appears when it’s in your court)
Update Owner, project manager
Create Revision Owner, project manager
Download (ZIP, PDF, or most recent attachments) Owner, project manager
Notify Users Owner, project manager
Delete Owner, project manager

A submittal has an overall status: Open, Draft, or Closed. Draft and closed submittals don’t send email notifications.

Each reviewer’s response has its own review status:

Review status Meaning
Approved Accepted as submitted
Approved as Noted Accepted with the reviewer’s comments, which must be followed
Reviewed Reviewed, without a formal approval or rejection
Revise and Resubmit Not accepted. Correct and send a new revision.
Rejected Not accepted
Void No longer needed
For Record Only Filed for information, no approval required
Submitted Sent for review
Pending No response yet

Yes. Click Export PDF on the Submittals list. Everyone on the project can export.

Yes. The SubmittalLink team can bulk-upload your existing submittal log, or extract one from your spec book. See Onboarding services.

Only owners and project managers can create submittals. If you are one and Create is still blocked, the project may have outstanding invoices. See Troubleshooting.